Contract No: HK/2009/05 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
1) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEp-06/364/2009/a and FEP-07/364/2009/A Monthly Environmental Monitoring
& Audit Report
- november 2011 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
14 December 2011 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring
6.4 Review
of the Reasons for and the Implications of Non-compliance
6.5 Summary
of action taken in the event of and follow-up on non-compliance
7. Cumulative Construction Impact due to the
Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/17
Table 3.3 Summary of submission status under FEP-03/364/2009
Table 3.4 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2009/01
Table 3.5 Summary of submission status under FEP-02/364/2009
Table 3.6 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2009/02
Table 3.7 Summary of submission status under FEP-01/364/2009
Table 3.8 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/18
Table 3.9 Summary of submission status under FEP-05/364/2009/A
Table 3.10 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/15
Table 3.11 Summary of submission status under FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/19
Table 3.13 Summary of submission status under FEP-07/364/2009/A
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring Stations
Table 4.3 Air Monitoring Stations
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.2 Noise Monitoring Stations for Contract no. HY/2009/18
Table 5.3 Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.4 Noise Monitoring Stations for Contract no. HY/2009/15
Table 5.5 Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.6 Real Time Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Air Monitoring Station for Contract no. HY/2009/17
Table 5.9 Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10 Air Monitoring Station for Contract no. HK/2009/01
Table 5.11 Air Monitoring Station for Contract no. HK/2009/02
Table 5.12 Air Monitoring Station for Contract no. HY/2009/15
Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table 5.14 Details of Waste Disposal for Contract no. HY/2009/17
Table 5.15 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.17 Details of Waste Disposal for Contract no. HY/2009/18
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.19 Details of Waste Disposal for Contract no. HY/2009/19
Table 8.1 Summary of Environmental Inspections for Contract no. HY/2009/15
Table 8.2 Summary of Environmental Inspections for Contract no. HY/2009/18
Table 8.3 Summary of Environmental Inspections for Contract no. HY/2009/19
Table 8.4 Summary of Environmental Inspections for Contract no. HK/2009/01
Table 8.5 Summary of Environmental Inspections for Contract no. HK/2009/02
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
lIST OF
FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action and
Limit Level
Appendix
4.2 Copies of Calibration
Certificates
Appendix
5.1 Monitoring Schedule for Reporting
Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical
Presentations
Appendix
5.4 Real-time Noise Monitoring Results and Graphical
Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Notification of Exceedance
Appendix
9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot
- Advanced piling works under FEP-03/364/2009
·
ELS works
for basement construction for pile cap construction.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
Instrumentation
works for Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Drainage
work at
·
Site
investigation and pre-drilling works at CR3
·
Diaphragm
wall construction
·
Hoarding
erection
·
Roadworks
at CR3
·
Grout
curtain
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
·
Diaphragm
wall construction works for CWB (Stage 1) and SCL protection works
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Tunnel
bored pile works at WCR1
·
Toe grout
at WCR1 area
·
Shear pin
at WCR1 area
·
Pumping
test at WCR1 area
·
King Post
at WCR area
·
Excavation
and lateral support at western Tunnel portion
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
Diaphragm
wall construction preparation works at TS4
·
Diaphragm
wall construction at TS1 and TPCWAE
·
Night
time protection works at CHT
·
Construction
of dewatering well at
·
Precautionary
works at Abutment A
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
·
Preparation
works and removal of existing marine
piles
·
Road
works at
·
Fabrication
of bored piling platform
·
Bored
piling
·
Ground
contamination assessment
·
D-wall Construction
·
Sheet
piling for Box Culvert T
Noise Monitoring
Air Monitoring
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/17 –
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works
under FEP-03/364/2009
·
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18 – Central – Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Instrumentation
works for Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Drainage
work at
·
Site
investigation and pre-drilling works at CR3
·
Diaphragm
wall construction
·
Hoarding
erection
·
Roadworks
at CR3
·
Grout
curtain
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at
·
Diaphragm
wall construction works for both CWB and SCL Protection Works within HKCEC1
·
Pre-drilling
works for CWB at Stage 2
·
Pilling
works for CWB at Stage 1
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Tunnel
bored pile construction works and ELS at western tunnel portion
·
Toe
grout, Shear pine, and Pumping test at WCR1 area.
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
·
Diaphragm
wall construction preparation works at TS4
·
ELS works
at TS1 and TPCWAE
·
Night
time protection works at CHT
·
Construction
of dewatering well at
·
Precautionary
works at Abutment A
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
·
Remove
existing dolphin
·
Road works
at
·
Fabrication
of bored piling platform
·
Bored
piling
·
Ground
contamination assessment
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall Construction
·
Sheet
piling for Box Culvert T
·
Construction
works for Box Culvert T
·
Marine
Piling
1.1.1.
Lam Geotechnics
Limited (LGL) has been appointed to work as the Environmental Team (ET) under
Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report
presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A
Manual and “Environmental Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009,
FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A during the period
28th October to 27th
November 2011. The cut-off date of reporting is at 27th of each reporting
month.
Section
1 Introduction
– details the scope and structure of the report.
Section
2 Project Background
– summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section
3 Status of Regulatory
Compliance – summarizes the status of valid
Environmental Permits / Licenses during the reporting period.
Section
4 Monitoring Requirements
– summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section
5 Monitoring Results
– summarizes the monitoring results obtained in the reporting period.
Section
6 Compliance Audit
– summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section
7 Cumulative Construction
Impact due to the Concurrent Projects –
summarizes the relevant
cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section
8 Site Inspection –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of
summons and Prosecution – summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
“Wan Chai
Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass
and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose
of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North
and North Point for construction of the Central-Wan Chai Bypass and Island
Eastern Corridor Link (CWB). Land formed under the project will be developed as
a world-class waterfront promenade joining that at the new Central waterfront
for public enjoyment.
2.1.3.
There is a
compelling and present need for the CWB to provide relief to the very congested
2.2.1.
Design and Construction of Central – Wan Chai Bypass and Island Eastern
Corridor Link under the Project involves the construction and operation of a
trunk road and its road tunnel more than 800m in length between portals that is
shown at Figure 2.1.
2.2.2.
The study area encompasses existing
developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
·
Tunnel
control buildings and ventilation buildings;
·
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
·
Associated
road lighting, road signing, traffic control and surveillance system; and
·
Other
associated works.
2.2.3.
The project also
contains various Schedule 2 DPs that, under the EIAO, require Environmental
Permits (Eps) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads |
Schedule
2, Part I, A.1 and A.7 |
Trunk
road and road tunnel more than 800 m in length |
DP2 |
Road P2
and other roads which are classified as primary/district distributor roads |
Schedule
2, Part I, A.1 |
Primary
/ district distributor roads |
DP3 |
Reclamation
works including associated dredging works |
Schedule
2, Part I, C.1 and C.12 |
Reclamation
more than 5 ha in size and a dredging operation less than 100 m from a
seawater intake point |
DP5 |
Wan Chai
East Sewage Outfall |
Schedule
2, Part I, F.5 and F.6 |
Submarine
sewage pipelines with a total diameter more than 1,200 mm and include a
submarine sewage outfall |
DP6 |
Dredging
for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule
2, Part I, C.12 |
A
dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the
multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
In the reporting
month, Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
was commenced on 13 July 2011. The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central –
Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central –
Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction
of Bus Terminus near |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai
Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East(CWB Tunnel)
|
DP1 |
26 April
2011 |
HY/2009/15 |
Central-Wanchai
Bypass – Tunnel ( |
DP1 |
13 July
2011 |
HY/2009/19 |
Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link |
DP1 |
24 March
2011 |
2.4.1.
Civil Engineering and Development Department and Highways Department are
the overall project controllers for the Wan Chai Development Phase II and
Central-Wan Chai Bypass respectively. For the construction phase of the
Project, Project Engineer, Contractor(s), Environmental Team and Independent
Environmental Checker are appointed to manage and control environmental issues.
2.4.2.
The proposed
project organization and lines of communication with respect to environmental
protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer
for WDII |
Principal
Resident Engineer |
Mr.
Frankie Fan |
2587
1778 |
2587 1877 |
Engineer
for CWB |
Principal
Resident Engineer |
Mr.
Peter Poon |
3916
1818 |
3529 2829 |
|
Lam Woo &
CO., LTD. |
Contractor
under Contract no. HY/2009/17 |
Project
Manager |
Mr. K.
S. Law |
9090
1378 |
2566 7522 |
Site
Agent |
Mr. Tony
Au |
9725
5874 |
2566 7522 |
||
Sub Agent |
Mr.
Johnny Wong |
9725
5870 |
2566 7522 |
||
Chun Wo
– Leader Joint Venture |
Contractor
under Contract no. HK/2009/01 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Mr. Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
Mr Jerry Siu |
9493 3664 |
|||
Construction Manager |
Mr Ricky Lai |
9487 6549 |
|||
Construction Manager |
Mr KK Yuen |
3498 1213 |
|||
Environmental Officer (Compliance
Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
Chun Wo
– CRGL Joint Venture |
Contractor
under Contract no. HK/2009/02 |
Project
Manager |
Mr. Chan
Sing Cho |
3658-3002 |
2827 9996 |
Site
Agent |
Mr. Mak
Kam Wing |
3658-3044 |
|||
Deputy
Site Agent |
Mr.
Anthony Wu |
3658-3004 |
|||
Quality
& Environmental Manager |
Mr. C.P.
Ho |
3658-3000 |
|||
Environmental
Officer |
Ms Flora
Ng |
3658-3064 |
|||
Chun Wo
– CRGL Joint Venture |
Contractor
under Contract no. HY/2009/19 |
Project
Manager |
Mr.
Rayland Lee |
3758 8879 |
2570 8013 |
Site
Agent |
Mr. Cheung
Kit Cheung |
6909
1555 |
|||
Environmental
Engineer |
Mr. Simon
Wong |
9281
4346 |
|||
Environmental
Manager / Environmental
Officer |
Mr. M.H.
Isa |
9884
0810 |
|||
Leighton
Contractors ( |
Contractor
under Contract no. HY/2009/18 |
Site
Agent |
Mr.
Brian Gillon |
2214 7700 |
|
Deputy
Site Agent |
Mr.
Desmond Sze |
2214 7703 |
|||
Environmental
Officer |
Mr.
Anfernee Chow |
2214 7721 |
|||
Environmental
Supervisor |
Mr.
Dennis Yu |
2214 7738 |
|||
Environmental
Supervisor |
Ryan
Tsui |
2214 7705 |
|||
|
Contractor
under Contract no. HY/2009/15 |
Project
Manager |
Mr. M Y
Wong |
2823
7879 |
2566 2192 |
Site
Agent |
Mr. P J
Fan |
3557
6368 |
|||
Head of
construction |
Mr. Roger
Cheung |
3557
6371 |
|||
Environmental
Officer |
Mr. Daniel
Sin |
3557
6215 |
|||
Environmental
Supervisor |
Mr. Kelven
Yip |
3557
6347 |
|||
Environmental
Supervisor |
Mr. Tim
Fung |
3557
6349 |
|||
|
|
Environmental
Supervisor |
Mr. Hilda
Lau |
3557
6378 |
|
ENVIRON
Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr.
David Yeung |
3743
0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work activities of individual
contracts are included as follows:
Contract no. HY/2009/17 –
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works
under FEP-03/364/2009
·
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18 – Central
– Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
Instrumentation
works for Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Drainage
work at
·
Site
investigation and pre-drilling works at CR3
·
Diaphragm
wall construction
·
Hoarding
erection
·
Roadworks
at CR3
·
Grout
curtain
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at
·
Diaphragm
wall construction works for CWB (Stage 1) and SCL protection works
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
·
Tunnel
bored pile works at WCR1
·
Toe grout
at WCR1 area
·
Shear pin
at WCR1 area
·
Pumping
test at WCR1 area
·
King Post
at WCR area
·
Excavation
and lateral support at western Tunnel portion
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (
·
Seawall
block construction, reclamation work and diaphragm wall construction
preparation works at TS4
·
Diaphragm
wall construction at TS1 and TPCWAE
·
Night
time protection works at CHT
·
Construction
of dewatering well at
·
Precautionary
works at Abutment A
Contract no. HY/2009/19 – Central
– Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link under FEP-07/364/2009/A
·
Preparation
works and removal of existing marine
piles
·
Road
works at
·
Fabrication
of bored piling platform
·
Bored
piling
·
Ground
contamination assessment
·
D-wall Construction
·
Sheet
piling for Box Culvert T
2.4.4.
In coming
reporting month, the principal work activities of individual contracts are
anticipated as follows:
Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD
Whitfield Depot – Advanced piling works under FEP-03/364/2009
·
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18 – Central – Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Instrumentation
works for Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Drainage
work at
·
Site
investigation and pre-drilling works at CR3
·
Diaphragm
wall construction
·
Hoarding
erection
·
Roadworks
at CR3
·
Grout
curtain
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at
·
Diaphragm
wall construction works for both CWB and SCL Protection Works within HKCEC1
·
Pre-drilling
works for CWB at Stage 2
·
Pilling
works for CWB at Stage 1
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Tunnel
bored pile construction works and ELS at western tunnel portion
·
Toe
grout, Shear pine, and Pumping test at WCR1 area.
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
·
Diaphragm
wall construction preparation works at TS4
·
Diaphragm
wall construction at TS1 and TPCWAE
·
Night
time protection works at CHT
·
Construction
of dewatering well at
·
Precautionary
works at Abutment A
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
·
Remove
existing dolphin
·
Road
works at
·
Fabrication
of bored piling platform
·
Bored
piling
·
Ground
contamination assessment
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall Construction
·
Sheet
piling for Box Culvert T
·
Construction
works for Box Culvert T
·
Marine
Piling
3.1.1.
A summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
3.1.2.
Due to the
multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract no. HY/2009/17 – Central
– Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
3.1.3.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table
3.2 and Table 3.3.
Table
3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 – 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3 Summary
of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization
of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and 2.8 |
Submission of works
schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus
near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4.
The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
3.1.5.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0384-11 |
29 Apr 2011 |
27 May 2011 to 26 Nov 2011 |
Expired |
|
GW-RS0680-11 |
22 Jul 2011 |
24 Jul 2011
to 19 Jan 2012 |
Valid |
|
GW-RS0689-11 |
28 Jul 2011 |
29 Jul 2011 to 28 Jan 2012 |
Valid |
|
GW-RS0832-11 |
7 Sep 2011 |
03 Sep 2011 to 02 Mar 2012 |
Valid |
|
GW-RS0850-11 |
12 Sept 2011 |
14 Sept 2011 to 13 Mar 2012 |
Valid |
|
GW-RS0851-11 |
12 Sept 2011 |
16 Sept 2011 to 15 Mar 2012 |
Valid |
|
GW-RE0683-11 |
16 Sept
2011 |
20 Sept 2011 to 19 Oct 2012 |
Valid |
|
GW-RE0716-11 |
28 Sept 2011 |
07 Oct 2011 to 29 Mar 2012 |
Valid |
|
GW-RS1094-11 |
23 Nov
2011 |
27 Nov
2011 to 26 May 2012 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar
2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account
under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan
2010 |
N/A |
Valid |
Table 3.5 Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May
2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
3.1.6.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for piling equipment |
PP-RS0011-11 |
27 April
2011 |
1 June
2011 to 30 Nov
2011 |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0369-11 |
21 April
2011 |
1 May
2011 to 31 Oct
2011 |
Expire |
|
GW-RS0377-11 |
27 April
2011 |
1 May
2011 to 31 Oct
2011 |
Expire |
|
GW-RE0311-11 |
4 May
2011 |
5 May
2011 to 31 Oct 2011 |
Expire |
|
GW-RS0401-11 |
3 May
2011 |
18 May
2011 to 17 Nov 2011 |
Expire |
|
GW-RS0414-11 |
3 May
2011 |
9 May
2011 to 8 Nov 2011 |
Cancel |
|
GW-RS0423-11 |
9 May
2011 |
22 May
2011 to 21 Nov 2011 |
Expire |
|
GW-RS0430-11 |
9 May
2011 |
16 May
2011 to 15 Nov 2011 |
Cancel |
|
GW-RS0453-11 |
19 May
2011 |
23 May
2011 to 22 Nov 2011 |
Expire |
|
GW-RS0458-11 |
17 May
2011 |
21 May
2011 to 20 Nov 2011 |
Cancel |
|
GW-RS0461-11 |
19 May
2011 |
23 May
2011 to 22 Nov 2011 |
Expire |
|
GW-RS0473-11 |
27 May
2011 |
01 May
2011 to 30 Nov 2011 |
Cancel |
|
GW-RS0496-11 |
31 May
2011 |
07 Jun
2011 to 06 Dec 2011 |
Valid |
|
GW-RS0502-11 |
8 Jun
2011 |
13 Jun
2011 to 12 Dec 2011 |
Valid |
|
GW-RS0579-11 |
22 June
2011 |
17 July
2011 to 16 Jan 2012 |
Valid |
|
GW-RS0645-11 |
18 July
2011 |
22 Jul
2011 to 21 Jan 2012 |
Cancel |
|
GW-RS0649-11 |
22 July
2011 |
1 Aug
2011 to 31 Jan 2011 |
Valid |
|
GW-RS0691-11 |
25 July
2011 |
27 July
2011 to 26 Jan 2011 |
Cancel |
|
GW-RS0716-11 |
2 Aug
2011 |
12 Aug
2011 to 11 Feb 2012 |
Valid |
|
GW-RS0722-11 |
2 Aug
2011 |
5 Aug
2011 to 5 Oct 2011 |
Expire |
|
GW-RS0723-11 |
12 Aug
2011 |
15 Aug
2011 to 14 Feb 2012 |
Valid |
|
GW-RS0833-11 |
8 Sept
2011 |
10 Sept
2011 to 4 Mar 2012 |
Valid |
|
GW-RS0857-11 |
16 Sept
2011 |
6 Oct
2011 to 5 Apr 2011 |
Valid |
|
GW-RE0710-11 |
30 Sept
2011 |
1 Nov
2011 to 30 Apr 2012 |
Valid |
|
GW-RS0918-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0929-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0930-11 |
11 Oct
2011 |
1 Nov
2011 to 30 Apr 2012 |
Valid |
|
GW-RS0931-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0941-11 |
20 Oct
2011 |
23 Nov
2011 to 22 May 2012 |
Valid |
|
GW-RS0955-11 |
14 Oct
2011 |
23 Nov
2011 to 22 May 2012 |
Valid |
|
GW-RS0968-11 |
20 Oct
2011 |
18 Nov
2011 to 17 May 2012 |
Valid |
|
GW-RS0983-11 |
24 Oct
2011 |
26 Oct 2011
to 23 April 2012 |
Valid |
|
GW-RS0984-11 |
25 Oct 2011 |
30 Oct
2011 to 27 April 2012 |
Valid |
|
GW-RS1028-11 |
3 Nov
2011 |
7 Dec
2011 to 6 June 2012 |
Valid |
|
GW-RS1052-11 |
18 Nov
2011 |
21 Nov
2011 to 18 May 2012 |
Valid |
Discharge
Licence |
WT00006249-2010 |
22 Mar
2010 |
31 Mar
2015 |
Valid |
|
WT00006436-2010 |
15 Apr
2010 |
30 Apr
2015 |
Valid |
|
WT00006673-2010 |
14 May
2010 |
31 Mar
2015 |
Valid |
|
WT00006757-2010 |
28 May
2010 |
31 May
2015 |
Valid |
|
WT00007129-2010 |
28 July
2010 |
31 Jul
2015 |
Valid |
|
WT00008982-2011 |
26 April
2011 |
30 April
2016 |
Valid |
|
WT00009691-2011 |
1 Aug
2011 |
31 July
2016 |
Valid |
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb
2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep
2010 |
N/A |
Valid |
Table 3.7 Summary
of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
21 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
28 Jun 2011 |
Condition 2.11 |
Landscape Plan |
23 Aug 2011 |
Condition 2.9 |
Noise Management Plan (Rev.A) |
28-Sep-11 |
Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
3.1.7.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-05/364/2009A for contract no.
HY/2009/18 are shown in
Table 3.8 and Table 3.9.
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0840-11 |
09 Sept 2011 |
09 Sept 2011 – |
Expired |
|
GW-RS0878-11 |
22 Sept
2011 |
22 Sept
2011 – |
Expired |
|
GW-RS0993-11 |
28 Oct
2011 |
28 Oct
2011 – |
Valid |
Discharge Licence |
WT00008229-2011 |
13 Jan 2011 |
31 Jan 2016 |
Valid |
Registration as a Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec 2010 |
Registration completed |
|
Application for a Billing Account for Disposal of Construction Waste (
Construction Work Contract with Value of $1 million or Above) under the Waste
Disposal Ordinance (Cap. 354) sections 5 & 9 of the Waste Disposal
(Charges for Disposal of Construction Waste) Regulation. |
Account No.: 7011587 |
11 Oct 2010 |
Account approved |
Valid |
Table 3.9 Summary
of submission status under FEP-05/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 4) |
3 August 2011 |
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
3.1.8.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.10 and Table 3.11
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov
2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0749-11 |
11 Aug 2011 |
15 Aug
2011 to 7 Feb
2012 |
Valid |
|
GW-RS1021-11 |
4 Nov 2011 |
10 Nov 2011 to 9 May 2012 |
Valid |
Construction Noise Permit (CNP) for
Installation of Instrumentation at CHT |
GW-RS0847-11 |
14 Sep 2011 |
19 Sep 2011 to 16 Mar 2012 |
Valid |
Construction Noise Permit (CNP) for
Diaphragm Wall Construction at TPCWAE |
GW-RS0858-11 |
16 Sep 2011 |
18 Sep 2011 to 16 Mar 2012 |
Valid |
Construction Noise Permit (CNP) for
Diaphragm Wall Construction at TPCWAE (24 hr) |
GW-RS0883-11 |
4 Oct 2011 |
5 Oct 2011to 4 Apr 2012 |
Valid |
Construction Noise Permit (CNP) for
Diaphragm Wall Construction at TS1 |
GW-RS0820-11 |
5 Sep 2011 |
8 Sep 2011
to 7 Mar 2012 |
Valid |
Registration as a
Chemical Waste Producer |
WPN:
5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
Billing Account under Waste
Disposal Ordinance (Dumping by Vessel) |
7011761 |
28 Apr 2011 |
1 May 2011 to 30 Oct 2011 |
Valid |
Water Discharge Licence (Discharge
at Portion VII) |
WT00008780-2011 |
22 Mar 2011 |
22 Mar 2011 to 31 Mar 2016 |
Valid |
Water Discharge Licence (Discharge
at |
WT00010482-2011 |
30 Sep 2011 |
30 Sep 2011 to 30 Sep 2013 |
Valid |
Table 3.11 Summary
of submission status under FEP-06/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition
2.6 |
Management
Organization of Main Construction Companies |
11 Mar 2011 |
Amendment
for Management Organization of Main Construction Companies |
16 May 2011 |
|
Condition
2.7 |
Works Schedule |
15 Mar 2011 |
Condition
2.8 |
Location
Plan |
15 Mar 2011 |
Condition
2.23 |
Noise
Management Plan |
6 May 2011 |
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
3.1.9.
The current status
on licences and/or permits on environmental protection pertinent and submission under
FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table 3.12 and Table 3.13.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste
Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Application for Vessel Disposal |
7012306 |
21 July 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) |
GW-RS1097-11 |
22-Nov-11 |
07-May-12 |
Valid |
Table 3.13 Summary
of submission status under FEP-07/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition 2.9 |
Noise Management Plan |
02 Jun 2011 |
Condition 2.13 |
Landscape Plan |
7 July
2011 |
Condition 2.9 |
Noise Management Plan(Rev.2) |
28-Oct-11 |
Noise Monitoring Stations
4.1.1.
The noise
monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.
Table
4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
M7e |
International Finance Centre
(Eastern End of Podium) |
M7w |
International Finance Centre
(Western End of Podium) |
Real time Noise Monitoring Stations
4.1.2.
Review of feasibility on the real time noise monitoring stations was
conducted in July with IEC. Station, RTN1a, Tung Lo Wan fireboat Station was
found not appropriate to be a monitoring station for monitoring the IECL Piling
works and Demolition after visited.
4.1.3.
The noise
monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the
monitoring works.
Table 4.2 Real
Time Noise
Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.4.
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for comparison
with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such
as L10 and L90 shall also be obtained for reference.
4.1.5.
Noise monitoring
shall be carried out at all the designated monitoring stations. The monitoring
frequency shall depend on the scale of the construction activities. The
following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One set of measurements between
0700 and 1900 hours on normal weekdays.
4.1.6.
Real time noise
shall be carried out at the designated monitoring stations. The following is an
initial guide on the regular monitoring frequency for each station on a 24
hours daily basis when noise generating activities are underway:
·
One set of measurements between
0700 and 1900 hours on normal weekdays.
·
One set of measurements between
1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public
holidays.
·
One set of measurements between
2300 and 0700 hours on next day on everyday.
4.1.7.
If construction
works are extended to include works during the hours of 1900 – 0700 as well as
public holidays and Sundays, additional weekly impact monitoring shall be
carried out during respective restricted hours periods. Applicable permits
under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.8.
As referred to
in the Technical Memorandum ™ issued under the NCO, sound level meters in
compliance with the International Electrotechnical Commission Publications 651:
1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying
out the noise monitoring. Immediately prior to and following each noise
measurement the accuracy of the sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.9.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
4.1.10. The sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements July be accepted as valid only if the calibration level from
before and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1.
The air
monitoring stations for the Project are listed and shown in Table
4.3 and Figure 4.1.. Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.3 Air
Monitoring Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North Point (Re-commenced on 14
November 2011) |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
|
Wan Chai |
MA1e |
International Finance Centre
(Eastern End of Podium) |
Central |
MA1w |
International Finance Centre
(western End of Podium) |
Central |
Remarks:
As per the ENPC meeting in March 2011, the monitoring stations CMA3a – Future
CWB site office at Wanchai Waterfront Promenade was renamed as remark.
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and
24-hour TSP levels should be measured to indicate the impacts of construction
dust on air quality. The 24-hour TSP levels shall be measured by following the
standard high volume sampling method as set out in the Title 40 of the Code of
Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant
data including temperature, pressure, weather conditions, elapsed-time meter
reading for the start and stop of the sampler, identification and weight of the
filter paper, and any other local atmospheric factors affecting or affected by
site conditions, etc., shall be recorded down in detail.
4.2.4.
For regular
impact monitoring, the sampling frequency of at least once in every six-days,
shall be strictly observed at all the monitoring stations for 24-hour TSP
monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three
times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume
samplers (HVSs) in compliance with the following specifications shall be used
for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6 – 1.7 m3 per minute
adjustable flow range;
·
Equipped with a timing / control
device with +/- 5 minutes accuracy for 24 hours operation;
·
Installed with elapsed-time meter
with +/- 2 minutes accuracy for 24 hours operation;
·
Capable of providing a minimum
exposed area of 406 cm2;
·
Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
·
Equipped with a shelter to
protect the filter and sampler;
·
Incorporated with an electronic
mass flow rate controller or other equivalent devices;
·
Equipped with a flow recorder for
continuous monitoring;
·
Provided with a peaked roof
inlet;
·
Incorporated with a manometer;
·
Able to hold and seal the filter
paper to the sampler housing at horizontal position;
·
Easily changeable filter; and
·
Capable of operating continuously
for a 24-hour period.
4.2.6.
Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be traceable
to the internationally recognized primary standard and be calibrated annually.
The concern parties such as IEC shall properly document the calibration data
for future reference. All the data should be converted into standard
temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
4.2.8.
Filter paper of
size 8” x 10” shall be labelled before sampling. It shall be a clean filter
paper with no pinholes, and shall be conditioned in a humidity-controlled chamber
for over 24-hours and be pre-weighed before use for the sampling.
4.2.9.
After sampling,
the filter paper loaded with dust shall be kept in a clean and tightly sealed
plastic bag. The filter paper shall then be returned to the laboratory for
reconditioning in the humidity controlled chamber followed by accurate weighing
by an electronic balance with readout down to 0.1 mg. The balance shall be
regularly calibrated against a traceable standard.
4.2.10. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.2.11. Current calibration certificates of equipments are
presented in Appendix
4.2.
5.0.1.
The
environmental monitoring will be implemented based on the division of works
areas of each designed project managed under different contracts with separate
FEP applied by individual contractors.
Overall layout showing work areas of various contracts, latest status of
work commencement and monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting
month, the concurrent contracts are as follows:
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
Contract no.
HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works under FEP-03/364/2009
Contract no.
HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
Contract no.
HY/2009/19 – Central – Wanchai Bypass Tunnel (North
Point Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Contract no.
HK/2009/02 Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan Chai
East
5.0.3.
The environment
monitoring schedules for reporting month and coming month are presented in Appendix
5.1.
5.1.1.
The noise
monitoring at stations were M1a and M5b during day time, M3a, M4b, M5b
and M6 during restricted hour were rescheduled on 13 October 2011 due to rain.
Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD
Whitfield Depot – Advanced piling works under FEP-03/364/2009
5.1.2.
The proposed
division of noise monitoring stations for Contract no. HY/2009/17 are
summarized in Table 5.1 below:
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria
Centre |
5.1.3.
No action and
limit level exceedance was recorded during day time and restricted hour period
in the reporting month. Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix
5.2.
Contract no. HY/2009/18 – Central – Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.1.4.
Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 5.2 below:
Table 5.2
Noise Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
5.1.5.
No action level and one limit level exceedance was recorded at M7e during
day time on 15 November 2011 in the reporting month. After checking contractor’s
work schedules and investigation found that drilling by drill rig and breaking
works for D-wall construction in front of IFC without noise barrier and no
abnormal work were observed through out the period of noise monitoring. As
such, the exceedance was considered project related.
5.1.6.
One non-project related limit level exceedance was
recorded on 21 November 2011 during restricted hours. Since traffic noise from
5.1.7. Noise monitoring results measured
in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Details of the Notification of Exceedance can be referred in Appendix
6.2.
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under
FEP-02/364/2009 and Contract no. HK/2009/02 – Wan Chai Development Phase II –
Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.8.
The commencement
of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under FEP-01/364/2009 is on 26
April 2011. The proposed division of noise monitoring stations are summarized
in Table
5.3 below.
Table 5.3
Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour
Road Sports Centre |
5.1.9.
An action level was recorded on 6 November 2011 due
to noise complaint received regarding one BC cutter and hoist were operated for
Diaphragm Wall construction of Shatin-Central Link to inspect bentonite pipes
and ensure no damages and all the joints are tightened in good position
regarding to Contractor of HK/2009/01.
5.1.10.
Four limit level exceedances were recorded at M1a –
Harbour Road Sports Centre on 31 October, 8, 15, 21 November 2011 during restricted hour for the
contractor of HK/2009/02. Major
noise source was contributed from
Contract no. HY/2009/15 – Central-Wanchai
Bypass – Tunnel (
5.1.11.
The commencement of construction works for Contract
no. HY/2009/15 under FEP-06/364/2009/A was on 13
July 2011. Noise monitoring was commenced on 13 July 2011.
The proposed divisions of noise monitoring stations
are summarized in Table 5.4 below.
Table
5.4 Noise
Monitoring Stations for Contract
no. HY/2009/15
Station |
Description |
M2b |
Noon Gun
Area |
M3a |
Tung Lo
Wan Fire Station |
5.1.12.
No action level and one non-project related limit level
exceedance was recorded on 21 November 2011 during restricted hours. Since traffic
noise from
5.1.13.
Noise monitoring
results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2
Contract no. HY/2009/19 – Central
– Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.1.14. Noise
monitoring for the tunnel works under contract no. HY/2009/19 was commenced on
24 April 2011. The proposed division of noise monitoring stations are
summarized in Table 5.5 below.
Table 5.5
Noise Monitoring Stations
for Contract
no. HY/2009/19
Station |
Description |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
|
M6 |
HK |
5.1.15.
No
action level and one limit level exceedance was recorded during day time period at
M6 on 31 October 2011 during day time was due to temporary
piling for construction of working platform for marine bored piling work by
vibratory hammer through out the period of noise monitoring. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 5.2
5.2.1.
No construction
activity with valid Construction Noise Permit was conducted during night time
period (2300 to 0700) in this reporting month.
Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD
Whitfield Depot – Advanced piling works under FEP-03/364/2009 and
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section)
and Island Eastern Corridor Link under
FEP-07/364/2009/A
Table 5.6 Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/17
Location
ID |
District |
Description |
RTN1 |
Tin
Hau |
FEHD Hong Kong Transport Section
Whitefield Depot |
Real time noise monitoring results and graphical
presentation during night time period are for information only.
5.2.3.
No project related action and limit level exceedance were recorded in
the reporting period. Real time noise monitoring results measured in
this reporting period are reviewed and summarized. Details of real time noise
monitoring results and graphical presentation can be referred to Appendix 5.4 .
5.2.4.
The proposed
division of noise monitoring stations are summarized in Table 5.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24 April 2011.
Table 5.7 Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/19
Location
ID |
District |
Description |
RTN1 |
Tin
Hau |
FEHD Hong Kong Transport Section
Whitefield Depot |
RTN2 |
North Point |
|
Real time noise
monitoring results and graphical presentation during night time period are for
information only.
5.2.5.
No project related action and limit level exceedance were recorded in
the reporting period. Real time noise monitoring
results measured in this reporting period are reviewed and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix 5.4 .
Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD
Whitfield Depot – Advanced piling works under
FEP-03/364/2009
5.3.1
The proposed
division of air monitoring stations are summarized in Table 5.8 below. Air
monitoring for the piling works under contract no. HY/2009/17 was commenced on
8 October 2010.
Table 5.8
Air
Monitoring Station for Contract no. HY/2009/17
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
|
5.3.2
Due to lack of electricity supply, 24hr-TSP was rescheduled from 18
November 2011 to 19 November 2011
5.3.3
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/18 – Central – Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.3.4
Air monitoring
for the Central Interchange works under contract no. HY/2009/18 was commenced
on 21 April 2011.The proposed division of air monitoring stations are
summarized in Table 5.9 below.
Table 5.9
Air
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International
Finance Centre (Eastern End of Podium) |
MA1w |
International
Finance Centre (Western End of Podium) |
5.3.5
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at
5.3.6
The commencement
of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air
monitoring stations are summarized in Table 5.10 below.
Table 5.10
Air
Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children
Playgrounds opposite to |
5.3.7
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.3.8
The commencement
of construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011.
The proposed division of air monitoring stations are summarized in Table
5.11 below.
Table 5.11
Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
5.3.9
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/15 – Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
5.3.10 The commencement of construction works for Contract
no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air quality
monitoring was commenced on 14 July 2011. The proposed division of air monitoring stations are
summarized in Table 5.12 below.
Table
5.12 Air Monitoring Station for Contract
no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE
Site Office |
No exceedance was recorded in the reporting month. Air quality
monitoring results measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/19 – Central
– Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link under FEP-07/364/2009/A
5.3.11
The proposed
division of air monitoring stations are summarized in Table 5.13 below. Air
monitoring for the tunnel works under contract no. HY/2009/19 was commenced on
26 April 2011.
Table 5.13
Air Monitoring
Stations
for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil St
Community Liaison Centre |
CMA2a |
Causeway
Bay Community Centre |
5.3.12
Since
the land located the Oil Street Community Liaison Centre will be handed-over to
Food and Environmental Hygiene Department (FEHD) for the construction of
temporary FEHD depot by the end of September 2011, the air monitoring station –
CMA1b was then temporary suspended on 18 September 2011. The permission of the
installation of HVS at temporary FEHD depot was obtained from the premises owner
on early November 2011 and TSP monitoring was recommenced on 14 November 2011.
5.3.13
Due to lack of
electricity supply, 24hr-TSP was rescheduled from 18 November 2011 to 19
November 2011
5.3.14
No exceedance
was recorded at CMA2a in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/17 –Central – Wan Chai
Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009
5.4.1.
No Inert C&D
waste was recycled in the reporting month. Details of the waste flow table are
summarized in Table 5.14
Table 5.14 Details
of Waste Disposal for Contract no. HY/2009/17
Waste Type |
Quantity
this month, m3 |
Cumulative
Quantity-to-Date, m3 |
Disposal
/ Dumping Grounds |
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
N/A |
||
Non-inert
C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
N/A |
N/A |
N/A |
Contract nos.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
5.4.2.
Inert and
non-inert C&D waste was disposed of in this reporting month. Details of the
waste flow table are summarized in Table 5.15.
Table 5.15 Details
of Waste Disposal for Contract no. HK/2009/01
Inert
C&D materials disposed |
254.20 |
5228.08 |
TKO137, TM38 |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
31.74 |
139.26 |
SENT Landfill |
Non-inert
C&D materials recycled |
5484 |
10463 |
N/A |
Chemical
waste disposed |
200 |
1300 |
Kwun Kee (Chemical Waste Collector) |
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
5.4.3.
Inert C&D &
non-inert C&D waste was disposed of in this reporting month. Details of the
waste flow table are summarized in Table 5.16.
Table
5.16 Details of Waste Disposal for Contract no.
HK/2009/02
Inert
C&D materials disposed |
7,342 |
57,450 |
TKO137, TM 38 |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
50 |
91 |
SENT Landfill |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
NIL |
1,104 |
N/A |
Contractor
clarified that no Inert and Non-inert
C&D materials disposed in June 2011
Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
5.4.4.
Inert C&D
and non-inert C&D waste was disposed of in this reporting month. Details of
the waste flow table are summarized in Table 5.17.
Table 5.17 Details
of Waste Disposal for Contract no. HY/2009/18
Inert
C&D materials disposed |
T.K.O. 137 |
||
Inert
C&D materials recycled |
N/A |
||
Non-inert
C&D materials disposed |
SENT Landfill |
||
Non-inert
C&D materials recycled |
N/A |
||
Chemical
waste disposed |
N/A |
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
5.4.5.
Inert & Non-inert C&D wastes were
disposed of in this reporting month. Details
of the waste flow table are summarized in Table 5.18.
Table 5.18 Details
of Waste Disposal for Contract no. HY/2009/15
Inert
C&D materials disposed |
172.2 |
2459.6 |
TKO137 FB |
|
15,281.1 |
15,281.1 |
Tuen Mun Area 38 |
Inert
C&D materials recycled |
109 |
413 |
N/A |
Non-inert
C&D materials disposed |
15.3 |
77.2 |
SENT Landfill |
Non-inert
C&D materials recycled |
NIL |
61.3 |
N/A |
Chemical
waste disposed |
NIL |
3,800 |
N/A |
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
5.4.6.
Only Non-inert
C&D waste was disposed of in this reporting month. Details of the waste
flow table are summarized in Table 5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/19
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
NIL |
630.954 |
N/A |
Non-inert
C&D materials disposed |
5.61 |
13.351 |
SENT Landfill |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
0.066 |
0.1 |
N/A |
6.0.1.
The Event Action
Plan for construction noise, air qualities are presented in Appendix 6.1.
Contract
no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works under FEP-03/364/2009
6.1.1.
No exceednace was recorded in the reporting month.
Contract
no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
6.1.2.
No action level and one project related limit level exceedance was
recorded on 15 November 2011 in the reporting month. After checking contractor’s
work schedules and investigation found that drilling by drill rig and breaking
works for D-wall construction in front of IFC without noise barrier and no
abnormal work were observed through out the period of noise monitoring.
6.1.3.
One non-project related limit level exceedance was recorded on 21
November 2011 during restricted hours. Since traffic noise from
Contract no. HK/2009/01 – Wan Chai Development Phase II –
Central – Wan Chai Bypass at
6.1.4.
No limit level and one
action level exceedance was recorded regarding a noise complaint received on 6
November 2011 due to one BC
cutter and hoist were operated for Diaphragm Wall construction of
Shatin-Central Link to inspect bentonite pipes and ensure no damages and all
the joints are tightened in good position.
Contract
no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.5.
No action level and four limit level exceedances were recorded at M1a –
Harbour Road Sports Centre on 31 October, 8, 15, 21 November 2011 during restricted hour. Investigation found that major traffic noise was contributed in the
noise monitoring and contractor complied with the requirement in valid
CNP during restricted hours noise monitoring.
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
6.1.6.
No action level and one non-project related limit level exceedance was
recorded on 21 November 2011 during restricted hours. Since traffic noise from
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.7.
No
action level and one project related limit level exceedance was
recorded during day time period at
M6 on 31 October 2011 during day time was due to temporary
piling for construction of working platform for marine bored piling work by
vibratory hammer through out the period of noise monitoring.
Real Time Noise Monitoring
Contract no. HY/2009/17 –
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009
6.1.8.
No exceednace was recorded in the reporting month.
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.9.
No exceednace was recorded in the reporting month.
Contract
no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot –
Advanced piling works under FEP-03/364/2009
6.2.1.
No exceedance was recorded in the reporting month.
Contract
no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
6.2.2.
No exceednace was recorded in the reporting month.
Contract
no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
6.2.3.
No exceednace was recorded in the reporting month.
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.2.4.
No exceednace was recorded in the reporting month.
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
6.2.5.
No exceednace was recorded in the reporting month.
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
6.2.1
No exceednace was recorded in the reporting month.
6.3.1.
There was no
non-compliance from the site audits in the reporting period. The observations
and recommendations made in each individual site audit session were presented
in Section 8.
6.3.2.
There was exceedance
of noise level recorded during day time on 31 October 2011 at M6 regarding to
temporary piling for construction of working platform
for marine bored piling work by vibratory hammer through out the period of
noise monitoring and 15 November 2011 at M7e that was considered in
relation to the drilling by drill rig and breaking
works for D-wall construction in front of IFC without noise barrier
during monitoring.
6.4.2.
Regarding to the
noise exceedance recorded at M7e, repeated measurement for noise monitoring
station would be conducted immediately once Limit Level exceedance recorded in
relation to Contract no. HY/2009/18, site investigations would be arranged
accordingly to observe and record the sources of the exceedance(s). During the
noise monitoring on 15 November 2011, drilling by drill rig and breaking works
for D-wall construction in front of IFC without noise barrier and no abnormal
work were observed through out the period of noise monitoring. Contractor had
suspended the works after received the notification on the same day to review
the plant operations. Contractor was advised to properly erect the noise
barriers as far as practicable for the drilling and breaking works. Additional
monitoring was conducted on 18 November 2011 at 11:30. Drill rig and breaker
operated at the concern area with fully erected moveable noise barrier,
drilling by drill rig and breaking works for D-wall construction were observed
during noise monitoring.
6.4.3.
No further
exceedance was recorded in the subsequent noise monitoring during
non-restricted hours at M6 and M7e. Nevertheless, the effectiveness of
remedial actions implemented by the Contractors will be continuously reviewed.
7.0.1.
According to
Condition 3.4 of the EP-364/2009/A, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East (CWB Tunnel).
7.0.2.
Monthly EM&A report (October 2011) of Central
Reclamation Phase III (CRIII) is outstanding in this reporting month, no cumulative
construction impact due to the concurrent activities of the current projects with
the Central Reclamation Phase III (CRIII) could be done.
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activity under Wan Chai Development Phase II
were the filling works at NPR2E, Seawall block construction, reclamation work
and diaphragm wall construction preparation works at TS4; Diaphragm wall
construction at TS1 and TPCWAE TCBR1W, maintenance dredging of navigation
channel and mooring area, HKCEC3w and marine bored piling at MTR Tunnel
Crossing. Advanced piling works at FEHD Whitfield Depot, Central Interchange,
cross-harbour water mains, tunnel works at WCR1 in the reporting month. The
major environmental impact was water quality impact at
7.0.4.
The major environmental impacts generated from advanced piling works at
FEHD Whitfield Depot were undertaken and sheet piling, pre-drilling and sheet
piling works at Central and tunnel works at Wan Chai East, IECL and
8.0.1.
During this
reporting month, weekly environmental site audits were conducted for Contracts
no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01 and HK/2009/02.
No non-conformance was identified during the site audits.
8.0.2.
Four site
inspections for Contract no. HY/2009/15 was carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.1.
Table 8.1 Summary
of Environmental Inspections for Contract no. HY/2009/15
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111101_01 |
1-Nov-11 |
Water
spraying shall be conducted especially those dust generating works
(TS4,TS1,EXTPCWA) |
Conduct
water spraying to dust generating works |
Completion
as observed on 8-Nov-11 |
111101_02 |
1-Nov-11 |
Oil
spillage shall be treated as chemical waste.(Abutment A) |
Collect
the contaminated top soil and treated as chemical waste. |
Completion
as observed on 8-Nov-11 |
111101_03 |
1-Nov-11 |
Protection
shall be improved for bentonite transshipment(EXTCPWA) |
Improve
the protection of bentonite transshipment |
Completion
as observed on 8-Nov-11 |
111101_04 |
1-Nov-11 |
Protection
of rock bund shall be improved to prevent any material loss.(TS4) |
Geotextile
shall be provided for the rock bund protection |
Completion
as observed on 8-Nov-11 |
111101_05 |
1-Nov-11 |
Silt
curtain at TS4 shall be maintained.(TS4) |
Maintain
the slit curtain at TS4 |
Completion
as observed on 8-Nov-11 |
111108_01 |
8-Nov-11 |
Enclosure
and ventilation system of grouting plant shall be improved |
Improve
the enclosure and ventilation system of grouting plant |
Completion
as observed on 15-Nov-11 |
111108_02 |
8-Nov-11 |
Protection
of the sloping seawall shall be provided, such as geotextile, to prevent any
leakage of the soil at reclamation. |
Geotextile
shall be provided for the slopping seawall protection |
Completion
as observed on 15-Nov-11 |
111115_01 |
15-Nov-11 |
Floating
refuses shall be collected (TS1, TS4) |
Collect
floating refuse |
Completion
as observed on 21-Nov-11 |
111115_02 |
15-Nov-11 |
Sandbags
shall be provided to protect the U channel (POC) |
provide
sandbags for U channel protection |
Completion
as observed on 21-Nov-11 |
111115_03 |
15-Nov-11 |
Drip tray
shall be provided for chemical storage (TS4) |
provide
drip tray for chemical storage |
Completion
as observed on 21-Nov-11 |
111121_01 |
21-Nov-11 |
Rectification
of southern seawall in terms of retrieving the
collapsed fill material and seawall block (TS4) |
Taking up
of collapsed fill material and seawall block |
In
progress |
111121_02 |
21-Nov-11 |
Seepage
of muddy water was observed at the tip of eastern sloping seawall (TS4). |
Maintain
the slit curtain at TS4 |
Completion
as observed on 29-Nov-11 |
8.0.3.
Four site
inspections for Contract no. HY/2009/18 was carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.2.
Table 8.2 Summary
of Environmental Inspections for Contract no. HY/2009/18
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
|
111103_01 |
3-Nov-11 |
Drip tray
shall be provided for chemical storage. |
provide
drip tray for chemical storage |
Completion
as observed on10-OCt-11 |
|
8.0.4.
Four site
inspections for Contract no. HY/2009/19 was carried out during this reporting
period. The results of these inspections
and outcomes are summarized in Table 8.3.
Table 8.3 Summary
of Environmental Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111102_01 |
2-Nov-11 |
The
contractor was reminded to clean the mud inside U channel to prevent
blockage. |
collect
the mud inside the U channel |
Completion
as observed on 9-Nov-11 |
8.0.5.
Four site
inspections for Contract no. HK/2009/01 was carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.4.
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111102_01 |
2-Nov-11 |
The
tarpaulin sheet between the hopper barge & Jetty barge shall be
maintained so as to have proper effectiveness. |
Maintain
the tarpaulin sheet between the hopper barge & Jetty barge |
Completion
as observed on 9-Nov-11 |
111102_02 |
2-Nov-11 |
Protective
measure at the site boundary(southern of HKCEC) shall be enhanced. |
Enhance
the protective measure at the site boundary |
Completion
as observed on 9-Nov-11 |
111109_01 |
9-Nov-11 |
The
effectiveness of sedimentation tanks at TST shall be reviewed and enhanced. |
Review
and enhance the effectiveness of sedimentation tanks |
Completion
as observed on 17-Nov-11 |
111117_01 |
17-Nov-11 |
The
stockpile located closed to the seawall at TST shall be covered by tarpaulin
sheet or trimming down. |
Cover the
stockpile by tarpaulin |
Completion
as observed on 23-Nov-11 |
111117_02 |
17-Nov-11 |
Contractor
was reminded to display relevant FEP and valid CNP at all site access. |
Display
relevant FEP and valid CNP at all site access. |
Completion
as observed on 23-Nov-11 |
111123_01 |
23-Nov-11 |
The silt
curtain at TST shall be maintained to ensure no gap to escape silty water. |
Maintain
the silt curtain |
Completion
as observed on 30-Nov-11 |
111123_02 |
23-Nov-11 |
Arrangement
of sedimentation tank located at HKCEC1 shall be reviewed to avoid any
over-flow of wastewater. |
Review
the arrangement of the sedimentation tanks at ex-Pet Garden |
Completion
as observed on 30-Nov-11 |
111123_03 |
23-Nov-11 |
Oil
leakage was observed from the drip trap for drill rig. The drip tray shall be
repaired to avoid any oil leakage. |
Repair
the drip tray |
Completion
as observed on 30-Nov-11 |
111123_04 |
23-Nov-11 |
Contractor
was reminded to place sand bags at the edge of seawall at TST and regular
trim-off the stockpile near seawall. |
Place
sand bags at the edge of seawall and regular trim-off the stockpile near it. |
Completion
as observed on 30-Nov-11 |
111123_05 |
23-Nov-11 |
Contractor
was reminded that no silty water shall be spillage from truck during the transportation.
|
Dehydrate
the soils/ materials properly before transportation |
Completion
as observed on 30-Nov-11 |
8.0.6.
Four site
inspections for Contract no. HK/2009/02 was carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.5.
Table 8.5 Summary
of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111103_01 |
3-Nov-11 |
Proper
dust suppression measure shall be provided on the jetty barge. Besides,
contractor was reminded to ensure the protective screen having appropriate
height to avoid C&D material drop into the sea. |
Provide
proper dust measure on the jetty barge and inspect the height of the
protective screen is appropriate to avoid C&D material drop into the sea |
Completion
as observed on 10-Nov-11 |
111103_02 |
3-Nov-11 |
Sand bags
shall be enhanced/replaced near eastern seawall. |
Replace
sandbags near eastern seawall |
Completion
as observed on 10-Nov-11 |
111110_01 |
10-Nov-11 |
The
effectiveness of wastewater treatment tank shall be checked and enhanced. |
Check and
enhance the effectiveness of wastewater treatment tank |
Completion
as observed on 16-Nov-11 |
111110_02 |
10-Nov-11 |
The
drainage system at ex-Pet Garden shall be reviewed to avoid any muddy water
overflow into the sea. |
review
the clearance of the drainage system at ex-Pet Garden |
Completion
as observed on 16-Nov-11 |
111116_01 |
16-Nov-11 |
Proper
clearance of the silt on the wheel of dump truck shall be provided before
leaving the site at |
Ensure
the mud on the wheels of dump trucks are fully cleaned before leave the site |
Completion
as observed on 24-Nov-11 |
111116_02 |
16-Nov-11 |
Contractor
was reminded to close the engine cover of the excavator at |
Ensure
the engine cover is closed of the plant before use |
Completion
as observed on 24-Nov-11 |
111124_01 |
24-Nov-11 |
The silt
curtain deployed at eastern seawall shall be weighted down to avoid
floating-up. |
maintain
the counter weight of the silt curtain |
Completion
as observed on 1-Dec-11 |
8.0.7.
Four site
inspections for Contract no. HY/2009/17 were carried out during this reporting
period. No observation was found in the reporting month.
9.0.1.
Two environmental
complaints were received on 4 and 6 November 2011 in the reporting month.
9.0.2.
The complainant, Mr. Liu from LCSD complained via
Contractor Complaint Hotline about a tree near the site of pipe installation
works outside Wan Chai Swimming Pool at
9.0.3.
A tree near the site of pipe installation works
outside Wan Chai Swimming Pool at
9.0.4.
Independent Tree Specialists for these two
inspected the trees. Contractor HK/2009/01 has taken the measure as recommend downgrading
the soil level around the trunk base. Reinstating of the ground works will be
conducted in mid-December 2011. For the tree no. TA1122 under Contract no.
HK/2009/02, the brown leaves were removed and fenced the tree with orange net
is provided to prevent damage of tree trunk by construction works. The distance
between the tree and the edge of the trench is kept approximate 2m. Two
Contractors were reminded to carry out regular watering to the trees within
their site area.
9.0.5.
A noise complaint was received by Police Officer
and a police officer arrived to Contract HK/2009/01 site at about 6:30 a.m. on
6 November 2011 to inspect noise generated from the site and stop the existed machines
operation. The subcontractor for Diaphragm wall, SAMBO Korean foreman stopped
the engine of the BC cutter immediately. The police officer recorded the
details and HKID number of the foreman and then left. Due to the different
language communication between the police officer and the Korean foreman, no
CNP was checked by the police officer.
9.0.6.
According to the information reported by Contractor,
one BC cutter and a hoist were operated for inspecting all bentonite pipes were
in good condition and all joints were tightened in good position for Diaphragm
Wall construction of Shatin-Central Link. Due to insufficient communication
between Contractor HK/2009/01 and their Korean Sub-contractor, the Korean
Sub-contractor had not notified to Contractor prior carrying out the inspection
of the bentonite pipes and all pipe joints to ensure no damages and was tightened
in good positions at about 6:00a.m.
9.0.7.
As such, the Contractor HK/2009/01 was reminded to
enhance the communication between Contractor and sub-contractor, and construction
Noise Permit should be checked and in place for the construction works during
restricted hour, plus providing environmental training to all foreman and
operators on restricted hour operation.
9.0.8.
The complaint was considered in relation to the
construction works during restricted hours without valid Construction Noise
Permit. No more construction works were conducted during night time period. The
construction works will be conducted in accordance with the time period stated
in valid CNP. This complaint will be kept in view of any follow-up action from
the relevant government activities.
9.0.9.
The details of cumulative complaint
log and updated summary of complaints are presented in Appendix
9.1
9.0.10. Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting
Period |
No. of
Complaints |
November 2011 |
2 |
Sep 10 to October 11 |
11 |
Total |
13 |
Table 9.2 Cumulative Statistics on Successful Prosecutions
Environmental
Parameters |
Cumulative
No. Brought Forward |
No. of
Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2. The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table 10.1 Summary of Key Construction Activities of Individual
Contract(s) to be commenced in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HY/2009/15 |
·
Diaphragm wall construction preparation works at TS4 ·
ELS works at TS1 and
TPCWAE ·
Night time protection
works at CHT ·
Construction of
dewatering well at ·
Precautionary works at
Abutment A |
·
Watering any dust
generating activities ·
Checking all drip trays
frequently and clear any stagnant water and mud
inside it. ·
Noise control measures
shall be provided during restricted hours. |
HY/2009/17 |
·
ELS works for basement
construction for pile cap construction. |
·
Noise barrier shall be
implemented; and ·
Watering any dust
generating activities |
HY/2009/18 |
·
Instrumentation works for
Manholes and Intake Culvert Survey ·
Excavation of trial pit ·
Drainage work at ·
Site investigation and
pre-drilling works at CR3 ·
Diaphragm wall construction ·
Hoarding erection ·
Roadworks at CR3 ·
Grout curtain |
·
Noise barrier shall be
implemented; and ·
Noise level shall be
controlled by reducing piling rate and no. of plants working in parallel. ·
Dust control during dust
generating works |
HY2009/19 |
·
Remove existing dolphin ·
Road works at ·
Fabrication of bored
piling platform ·
Bored piling ·
Ground contamination assessment ·
Pre-drilling works for
bored pile and Diaphragm wall ·
D-wall Construction ·
Sheet piling for Box
Culvert T ·
Construction works for
Box Culvert T ·
Marine Piling |
·
Noise level shall be
controlled by reducing the operation rate. ·
Noise barrier shall be
deployed for dolphin pier removal. |
HK2009/01 |
·
Diaphragm wall
construction works for both CWB and SCL Protection Works within HKCEC1 ·
Pre-drilling works for
CWB at Stage 2 ·
Pilling works for CWB at
Stage 1 |
·
Noise level shall be
controlled by reducing pilling rate. ·
Well maintain the
enclosures for grouting and bentonite mixing plants. ·
Apply CNP for night
works, if necessary. |
HK/2009/02 |
·
Tunnel bored pile
construction works and ELS at western tunnel portion ·
Toe grout, Shear pine,
and Pumping test at WCR1 area. |
·
Noise level shall be
controlled by reducing pilling rate. ·
Well maintain the
enclosures for grouting and bentonite mixing plants. |
10.0.3. The construction works of Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near